Pillar 01 · Co-PM
Runs the PM's work, not the engineer's.
The TR1/TR8 is sealed by the RDP. Laboro runs the PM's work: coordinate the inspection, get the work ready to pass, and hand the engineer a served package.
DOB NOW · Permit M01234567-I-SH · ACTIVE
synced 2 h ago
Compliance timeline · 412 Rowan Street
-
✓Sidewalk Shed / Supported Scaffold PermitPermit M01234567-I-SHComplete
-
✓Protection verified on sitePedestrians + adjacent propertyComplete
-
3Masonry Brick & Mortar InspectionBC 1705.4 · Special inspectionNext PM action
-
4Structural steel probesPending
-
5Terra-Cotta Patching & ReplacementPending
-
6Re-pointing (floors 14-15, North)Pending
-
7Final Inspection per Directive 14/75Pending
Pillar 02 · Critical path
Which milestone moves the date — and which doesn't.
Laboro computes the dependency chain from the plans and tells you which milestone moves the sign-off date — and which one has slack.
6 of 8 milestones on the critical path
The length of the critical chain defines FISP sign-off. Everything else is slack.
Dependency chain · 412 Rowan Street
-
✓Sidewalk Shed / Scaffold PermitCriticalComplete
-
✓Protection verifiedCriticalComplete
-
3Masonry Removal & Inspection (BC 1705.4)CriticalIn progress
-
4Structural steel probesConditional · 3 d slack
-
5Terra-Cotta Patching & ReplacementCritical
-
6Re-pointing floors 14-15 (North)Critical
-
7Joint sealant5 d slack · can overlap
-
8Final Inspection Directive 14/75CriticalEnd · Sign-off
Current bottleneck
Masonry inspection (BC 1705.4)
Blocks Terra-cotta and Re-pointing. A delay here pushes FISP sign-off 1:1.
Approving Masonry enables in parallel:
→Terra-Cotta Patching & Replacement — critical, starts immediately.
→Structural steel probes — 3 d slack, can be sequenced without moving the date.
Available slack
2 milestones with slack — Joint sealant (5 d) and Structural steel probes (3 d) — can be reordered without moving the sign-off date.
Pillar 03 · Live portal
The report becomes a living deliverable.
The owner stops asking for updates by email: they see real progress, live, with evidence.
L
Owner view · 412 Rowan Street
0%Progress
Compliance progress
2 of 7 milestones completed · Masonry in progress this week
Masonry (BC 1705.4)In progress
Terra-cottaPending
Re-pointingPending
Final · Dir. 14/75Pending
Recent evidence
East Facade · Jul 11
14th Floor North · Jul 10
Shed Rowan St · Jul 9
Last updated 2 h ago